Panhandle of Texas Chapter AGC

 

 

 

 

 

 

Bid Results

 

 

Bid Date Thursday, April 29, 2010 at 2:00 PM

Project: CISD Reeves-Hinger Elementary Renovations

Bidder  Base Bid
   

1.   CRUZ CONSTRUCTION

735,000.00
2.  Kelly Wood Company   753,000.00
3. Perry Williams Inc. 765,008.00
4. SOUTHWEST GENERAL CONSTRUCTION 766,397.00
5. WILEY HICKS JR., INC. 784,900.00
6. Plains Builders       815,676.00
7. Panhandle Steel Buildings 863,766.00
8.   
9.   

 

Cruz Construction used the following sub-bidders and suppliers in submitting the general contractors bid.

                                                                                                 

CATEGORY: FIRM:
SITE WORK
CONCRETE

LANDSCAPING

MASONRY

STEEL  

STEEL ERECTION
MILLWORK American Millwork
ROOFING & SHEET METAL
CAULKING
HOLLOW METAL
OVERHEAD DOORS
WINDOWS Amarillo Area Glass
FINISH HARDWARE
GLASS & GLAZING
DRYWALL Denman
LATH & PLASTER
CERAMIC TILE
ACOUSTIC CEILINGS Denman
RESILIENT FLOORING A-1 Flooring
CARPET A-1 Flooring
PAINTING Jack Thomas
MECHANICAL Vaseck/ AC Plumbing
ELECTRICAL American Electric

  SUB-BIDDERS AND SUPPLIERS HAVE BEEN LISTED FOR THE BASE BID ONLY.

ALTERNATES COULD AFFECT THE SUB-BIDDERS AND SUPPLIERS LISTED.

This list is submitted solely for the purpose of improving sub contract bidding practices and the list of sub-bidders and suppliers named above does not constitute an agreement or contract between general contractor and sub-bidder that the sub-bid is accepted by the general contractor or must or shall be used in performing the general contract.  General contractor, owner or architect shall have the right to reject any sub-bid made by a sub-bidder named in the list when, in the exclusive opinion of the general contractor, owner or architect, the sub-bidder is not considered qualified to perform or complete the sub-bid in the manner and time called for in the contract documents.  The rejection of any sub-bid used in submitting a general contract bid as named in the list shall not create any responsibility of any nature to a reject sub-bidder, regardless of such sub-bidders or suppliers being named in the list.

Home | General Contractors | Associate Members | Chapter News | 4 HR  Bid Plan Rules | Plans Available | Bid Results | Contact Us

 
For problems or questions regarding this web contact agcama@suddenlinkmail.com.
Last updated: 03/31/09.